The Wisconsin State Building Commission met on Thursday, February 27, to vote on state and UW System building and improvement proposals. The Commission considered and approved the following items on behalf of the University of Wisconsin:
- UW-La Crosse: Authority to Construct the Fieldhouse and Soccer Support Facility – $49,035,000 ($24,517,500 PRSB and $24,517,000 PR-Cash)
- UW-Madison: Increase for the Babcock Hall Dairy Plant and Center for Dairy Research Addition $25,689,100 – $72,609,100 ($26,210,000 GFSB, $23,960,000 Gifts and $22,439,100 PR-Cash)
- UW-Madison: Increase for the Meat Science and Muscle Biology Laboratory $7,000,000 – $57,077,000 ($27,177,000 GFSB, $25,400,000 Gifts and $4,500 PR-Cash)
- UW-Madison: Authority to Construct the Sellery Hall Addition and Renovation – $78,811,000 ($59,108,000 PRSB and $19,703,000 PR-Cash)
- UW-Milwaukee: Increase, Authority to Demolish Building A, Authority to Construct NWQ and Student Health Projects – $3,100,000 – $59,780,000($49,100,000 GFSB, $7,000,000 PRSB, $1,500,000 PR-Cash and $2,180,000 Gifts)
- UW Eau Claire: Increase, Heating Plant Fuel Reliability – $1,057,400 -$3,857,200 ($2,709,300 GFSB and $1,147,900 PRSB)
- UW-Parkside: Increase, Authority to Construct Classroom Renovation/Instructional Technology $450,000 PR-Cash – $2,501,300 ($2,051,300 GFSB and $450,000 PR-Cash)
- UW-Milwaukee: EMS Laboratory Renovation – $2,990,000 GFSB
- UW-Milwaukee: Purin Hall Infrastructure Repairs – $325,000 PRSB
- UW-Milwaukee: Zelazo Center Roof Repairs – $930,000 GFSB
- UW-Milwaukee: Campus IT Infrastructure Renovation – $4,805,100 ($3,748,000 GFSB and $1,057,100 PRSB)
- UW-Milwaukee: Heating Plant Stack Replacements – $526,000 ($410,000 GFSB and $115,700)
- UW-Parkside: Sports & Activity Center Pool Basin Infill – $1,764,600 GFSB
- UW-Parkside: Campus Underground Utility Distribution Renovation – $4,847,400 ($4,023,300 GFSB and $824,100 PR-Cash)
- UW-Platteville: Art Building Exterior Envelope Repairs – $2,424,400 GFSB
- UW-Platteville: Williams Fieldhouse Addition Roof Replacement – $1,378,300 GFSB
- UW-River Falls: Increase, Heating Plant Fuel Reliability Upgrade – $473,000 – $3,288,700 ($1,331,400 GFSB and $1,956,800 PR-Cash)
- UW-Stout: Multi-Bldg Fire Alarm System Replacement – $2,045,000 GFSB
- UW-Whitewater: Esker Hall Roof Replacement – $1,195,000 PRSB
- UW-Whitewater: Heating Plant Boiler No. 6 Upgrade – $400,000 ($228,000 GFSB and $172,000 PRSB)
Meeting minutes will be posted on the DFDM website once they are available.